It is expected that the demand for water in the Durban metropolitan area will exceed supply from all current sources over the next ten years. The existing water supply network from the uMngeni River is insufficient to meet the projected growth in demand.
Phase 1 of the project (uMWP-1) will comprise the Smithfield Dam, a raw water tunnel to Baynesfield, the Langa buffer dam, and a water treatment plant and raw water pipeline in the Baynesfield area.
Our subsidiary will be responsible for designing and supervising the construction of a 21.3 kilometre-long, 2,800/2,600 millimetrediameter steel drinking water pipeline, as well as carrying out related works.
WANT TO TAKE PART IN MAJOR PROJECTS? JOIN US!
KHH for geotechnical works>br/>Nemai for environmental work
Types of services
Dam heightening and new spilway (piano key weir type)
Ingérop South Africa (ISA) was appointed by Department of Water Affairs (DWA), to attend to the project for the raising of the Hazelmere Dam in KwaZulu-Natal.
The Raising of the Hazelmere Dam consists of the Design, Manufacture and Installation of Crest Gates and associated infrastructure. The project includes civil works to ensure the overall stability of the dam wall and provision for emergency overflow in case the gates do not open on time.