Types of services
The Malaga metropolitan/tram system has a total length of 14.1 km, 78% of which is underground. It is divided into a common axis 2.3 km long, two branches (lines 1 and 2), 8.1 km and 4.0 km long respectively, with a total of 21 stops (6 of which are above ground). Metro de Málaga commissioned Ingerop to manage the construction of the facilities for Lines 1 and 2.
Activities carried out:
· Checking and monitoring the correct execution of the contracted works.
· Ensuring quality and quantity.
· Compliance with occupational health and safety on site.
· Monitoring of the Environmental Surveillance Plan.
· Technical advice and technical distributions.
· Interface management.
· Responsible for all matters related to the installation of tunnels, stations, stops, above-ground sections, workshops, central control station, and depots, as well as all railway and non-railway facilities associated with the operation.