Project USAN

Client

TRELLEBORG INDUSTRIE

Mission

Sizing study

Lieu

Clermont-Ferrand (63)

Design study and finite elements calculations for the modification of traction bench elements subjected to new tests, carried out on offshore pipelines.

Realization study, manufacturing and installation of new equipment. Installation of a force measuring system with compression sensor and gauge bridge.

Tasks in design phase

  • Sizing of new elements of the traction bench using finite element calculating software (SolidWorks Simulation)
  • Detailed Pre-Project Plans
  • Calculation notes and summary of results

Tasks in realization phase:

  • Implementation plans
  • Dismantling of existing elements
  • Reassembly of new elements
  • Installation of a strain gauge bridge
Project USAN