Cold production units project EG0 - EG10

Client

ADISSEO

Mission

General contractor

Lieu

COMMENTRY (03)

- Realization of a new cold glycoled water production of 0° C and -10 ° C to replace the existing cold ammonia-based production (2 groups of 750 kW)

Task comprises:

* Creation of a technical room to house new cooling-water production units working on R410a.

- Equipment concerned:

* Equipment supply

* Civil engineering / waterproofing / finishing work

* Metal structures / blacksmithing / handling

* Piping / insulation / scaffolding

* Ventilation

* Instrumentation